Baffle Creek delivered before the deluge

October 19, 2017

 

In record time, Pipeline Drillers has replaced a 365 metre section of gas pipeline in Lowmead, north of Bundaberg for APA Group.

 

The crew installed the new 100 millimetre steel pipe beneath Baffle Creek, finishing two weeks ahead of schedule and before the spring deluge hit forcing many locals to evacuate.

 

Working 6 days a week to limit time working within private property, the team made a flying start with the pilot hole completed within millimetres of the mark (as pictured below).

 

Pipeline Drillers safely installed the pipe spending just eight days on site, again demonstrating efficient execution of horizontal directional drilling.  View this project and others here.