NACAP Esso - rail
NACAP Esso - rail
NACAP Esso - rail
NACAP Esso
NACAP Esso
NACAP Esso
NACAP Esso

CLIENT

NACAP Australia

LOCATION

Longford, VIC

DURATION

2016-2017

CROSSING UNDER

Roads, Railways, Services & Creeks
Oil & Gas

PRODUCT

14" Steel Pipe & 6" FOC lines

PRODUCT PIPE

BORE LENGTHS

363m, 592m, 690m, 345m, 385m, 435m & 395m

GEOLOGY

OTR, Clay & Rock

DINGO GAS FIELD DEVELOPMENT PIPELINE

Dingo Gas Development Project
Dingo Gas Development Project
Dingo Gas Development Project
Dingo Gas Development Project

CLIENT

Central Petroleum

LOCATION

Alice Springs, NT

DURATION

February 2015

CROSSING UNDER

Rail Easement
Gas

PRODUCT

250mm HDPE & 4" Steel Pipe

PRODUCT PIPE

BORE LENGTHS

2 x 75m

GEOLOGY

Sandy Clay

WHEATSTONE ASHBURTON PIPELINE

Welding
Welding
Pipe Ramming
Pipe Ramming
Grundoram Goliath

CLIENT

Monadelphous KT Pipelines

LOCATION

Wheatstone, WA

DURATION

November 2014

CROSSING UNDER

Rail Easement
Gas

PRODUCT

16" Steel Pipe

PRODUCT PIPE

BORE LENGTHS

2 x 60 metres

GEOLOGY

Cobble

BYRON BAY SHIRE COUNCIL SEWERAGE PIPELINE

s - 2

CLIENT

Diona

LOCATION

Brunswick Heads, NSW

DURATION

December-February 2009
Rail Easement

PRODUCT

Sewer

PRODUCT PIPE

500mm HDPE

BORE LENGTHS

400m

GEOLOGY

Sandy Clay

CROSSING UNDER

NACAP AUSTRALIA ESSO LONGFORD PIPELINE 

+61 7 3390 4740   |   sales@pdgroup.com.au

© 2016 by Lana Whitbread and proudly created with Paul Tredenick. 

Privacy Statement