DEMACS CONSTRUCTIONS - M1 VARSITY LAKES TO TUGUN
![]() | ![]() | ![]() |
---|---|---|
![]() |
CLIENT
Demacs Constructions
LOCATION
Currumbin, Queensland
DURATION
August 2020 - December 2020
CROSSING UNDER
Major Creek
PRODUCT
Potable Water, Recycled Water and Sewer
PRODUCT PIPE & BORE LENGTHS
2x 630mm PN20 HDPE, 1x 560mm PN16 Enveloper with 400mm PN16 Product, 1x 800mm PN16 Enveloper with 560mm PN16 Product
GEOLOGY
Sands
FULTON HOGAN - WASTEWATER TREATMENT PROGRAM JINDALEE
![]() | ![]() | ![]() |
---|---|---|
![]() |
CLIENT
Fulton Hogan Utilities Pty Ltd
LOCATION
Jindalee, Queensland
DURATION
July 2020 - December 2020
CROSSING UNDER
Golf Course and Highway
PRODUCT
Sewer Rising Main
PRODUCT PIPE
BORE LENGTHS
670m & 290m
GEOLOGY
Argillite and Hard Rocks
560mm PN20 HDPE & 800mm PN16 HDPE
SOUTHERN PROGRAM ALLIANCE - MENTONE DEWATERING HDD WORKS
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() |
CLIENT
Lendlease Engineering Acciona Coleman Rail JV
LOCATION
DESIGN
Undertaken by Pipeline Drillers design team
Mentone, Victoria
DURATION
November 2019 - January 2020
CROSSING UNDER
Railway
PRODUCT
Water
PRODUCT PIPE
Drill pipe casing with internal slotted pipe
BORE LENGTHS
1050m
GEOLOGY
Silty sands and clay
GLADSTONE REGIONAL COUNCIL – AUCKLAND CREEK
![]() |
---|
CLIENT
Gladstone Regional Council
LOCATION
Auckland Creek, Gladstone, QLD
DURATION
December 2019
CROSSING UNDER
Creek
PRODUCT
Sewerage
PRODUCT PIPE
710mm PN20 HDPE
BORE LENGTHS
160m
GEOLOGY
Sandy gravel and clayey ground
ISLE OF CAPRI BRIDGE - COUNCIL OF THE CITY OF GOLD COAST
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
CLIENT
Council of the City of Gold Coast
LOCATION
Isle of Capri Bridge, Gold Coast
DURATION
October - November 2019
CROSSING UNDER
River
PRODUCT
Sewerage
PRODUCT PIPE
2 x 710mm HDPE
BORE LENGTHS
270m & 140m
GEOLOGY
Sand, silty sand
FULTON HOGAN SEYMOUR WHYTE JOINT VENTURE - CALOUNDRA
![]() | ![]() | ![]() |
---|---|---|
![]() |
CLIENT
Fulton Hogan Seymour Whyte Joint Venture
LOCATION
Caloundra, QLD
DURATION
March - June 2019
CROSSING UNDER
Caloundra Road
PRODUCT
Water
PRODUCT PIPE
710mm PN20 HDPE
BORE LENGTHS
800 meters
GEOLOGY
Various ground conditions
FB CONTRACTING - NARRABRI CREEK
BMD BAC RECYCLED WATER MAIN
BMD BAC RECYCLED WATER MAIN
![]() | ![]() |
---|
CLIENT
FB Contracting
LOCATION
Narrabri Creek, NSW
DURATION
February - March 2019 - 3 weeks in total
CROSSING UNDER
Environmentally Sensitive Area,, Narrabri Creek
PRODUCT
Rising Water Main, Truck Water Main
PRODUCT PIPE
315mm, 400mm
BORE LENGTHS
400mm @ 220m, 315mm @ 220m
GEOLOGY
Sand, Fine Gravels, Clayey Sand and Cobble
WATER CORPORATION GROUND WATER REPLENISHMENT SCHEME - STAGE 2
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
CLIENT
Water Corporation
LOCATION
Perry's Paddock and Banksia Woodlands WA
DURATION
June - October 2018
CROSSING UNDER
Major Highway and Protected Wetland
PRODUCT
Water
PRODUCT PIPE
DN800, PN20
BORE LENGTHS
530m , 1,340m
GEOLOGY
Sand, Silty Sand, Peat/Organic Material
WOORIM, BRIBIE ISLAND OCEAN OUTFALL
![]() | ![]() | ![]() |
---|
CLIENT
Slurry Systems Marine
LOCATION
Woorim Beach, Bribie Island, QLD.
DURATION
Late August - September 2018
CROSSING UNDER
Ocean Outfall
PRODUCT
Sewerage
PRODUCT PIPE
450mm HDPE
BORE LENGTHS
175m
GEOLOGY
Fine to Medium Sand
BMD BAC RECYCLED WATER MAIN
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() |
CLIENT
BMD
LOCATION
Brisbane Airport, QLD
DURATION
September - October 2017
CROSSING UNDER
Airway, Roads & Creeks
PRODUCT
Recycled Water
PRODUCT PIPE
DN 350mm, DN 450mm, DN 560mm HDPE
BORE LENGTHS
90m, 109m, 114m, 150m, 795m
GEOLOGY
Marine Clays & Sand
CALOUNDRA & MOUNTAIN CREEK TO KAWANA SEWERAGE PIPELINES
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() |
CLIENT
Unitywater
LOCATION
Sunshine Coast, QLD
DURATION
March 2017 - 2018
CROSSING UNDER
River and Roads
PRODUCT
Sewage
PRODUCT PIPE
900mm HDPE
BORE LENGTHS
1.6km, 1.2km, 908m, 315m
GEOLOGY
Clay, Sand, Rock
M&K MAROOCHYDORE RISING MAIN
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
![]() |
CLIENT
M&K Pipelines
LOCATION
Maroochydore, QLD
DURATION
November 2016
CROSSING UNDER
Street
PRODUCT
Sewerage
PRODUCT PIPE
630mm HDPE
BORE LENGTHS
347 metres
GEOLOGY
Sand/Clay
BRADY MARINE RUBYANNA WASTE WATER OUTFALL
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
CLIENT
Brady Marine & Civil
LOCATION
Bundaberg, QLD
DURATION
September - November 2016
CROSSING UNDER
River Outfall
PRODUCT
Water
PRODUCT PIPE
800mm HDPE
BORE LENGTHS
2 x 56 metres
GEOLOGY
Clay/Rock
BMD TOWNSVILLE ROSS RIVER RISING MAIN
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
![]() | ![]() |
CLIENT
BMD Townsville
LOCATION
Townsville, QLD
DURATION
July - September 2016
CROSSING UNDER
Street and River
PRODUCT
Water
PRODUCT PIPE
450mm HDPE
BORE LENGTHS
380 metres
GEOLOGY
Rock
CAIRNS REGIONAL COUNCIL RISING MAIN K with JPMI
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() |
CLIENT
JPMI - Cairns Regional Council
LOCATION
Cairns, QLD
DURATION
May 2016 - June 2016
CROSSING UNDER
Services and Easements
PRODUCT
Water
PRODUCT PIPE
1000 mm HDPE PN16
340 metres
BORE LENGTHS
GEOLOGY
Sand/Clay
UNITYWATER WEYBA CREEK
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() |
CLIENT
Unitywater
LOCATION
Noosa, QLD
DURATION
November 2015
CROSSING UNDER
Creek
PRODUCT
Water
PRODUCT PIPE
315 mm HDPE
BORE LENGTHS
308 metres
GEOLOGY
Sand/Marine Mud
YAMBA 450mm HDPE OCEAN OUTFALL
![]() | ![]() | ![]() |
---|