Project Thenus - Stage 2
ABLP | Kingscliff, NSW | Jul – Nov 2022
Scope
Stage 2 works involving three onshore HDD
installations and two × 1,100m ocean outfalls.
Challenges
Pipeline Drillers enlisted marine subcontractors
to float the pipe offshore and connect it to the
drill string for installation.
Outcome
Successful completion of onshore installationsand ocean outfalls, including coordinatedoffshore pipe flotation and pullback activities.
-
2 × 1,100m OCEAN OUTFALLS
-
260m, 560m, 320m, 380m
-
500mm & 560mm HDPE