Lytton Terminal Expansion Project

IOR | Brisbane, QLD | Sep 2022 – Apr 2023

Scope

HDD installation works within a constrained corridor
at the Port of Brisbane, including installation of 610mm
steel pipeline.

 

Challenges

Pipeline Drillers commenced the hole expecting
manageable ground conditions, however were soon faced
with fractured ground consisting of cobbles and gravels.
Additional geotechnical investigations were conducted to
investigate the ground conditions at differing depths.

 

Outcome

The team worked on a double shift rotation to ensure the
ground conditions could be effectively managed and
achieve a successful pipe installation. The project involved
the stringing, welding and field joint coating of 158 lengths
of pipe, including a golden weld during pullback activities.

  • 2,000m, 220m, 80m
     
  • 610mm STEEL PIPE
     
  • RIVER CROSSING