Perth Groundwater Replenishment Scheme
Water Corporation | Joondalup, WA | Jul – Nov 2018
Scope
HDD installation of 800mm HDPE pipelines across 1,350m and 550m bores as part of the Perth Groundwater Replenishment Scheme.
Challenges
Due to the highly environmentally sensitive area, Pipeline Drillers identified areas for improvement within the design and elected to combine two of the three bores to eliminate the required footprint and mitigate environmental impact.
Outcome
Pipeline Drillers were commended on their efforts in delivering this project on time, on budget and without incident.
-
1,350m & 550m BORES
-
800mm HDPE
-
SANDS & PEAT / ORGANICS