top of page
Onslow Desalination Plan
Austral | Onslow, WA | May – Oct 2025
Scope
Installation of desalination plant pipeline infrastructure using
HDD, including three parallel 660m bores for seawater
intake and a 965m pilot hole for the outfall pipeline.
Challenges
The works required precise bore alignment beneath the
seabed, including accurate pilot drill exits into casing
installed from a jack-up barge. GPS track, real-time gyro
measurements and expert steering were used to verify
trajectory and maintain positional accuracy throughout the
crossings.
Outcome
All four pilot bores were completed successfully, enabling
installation of the desalination plant pipelines. The works
were completed ahead of time and support a more reliable
drinking water supply for the Onslow area.
-
SEABED CROSSING
-
3 X 660m + 965m PILOT
-
225mm, 250mm & 2 X 450mm PIPE


bottom of page